The Rebuild

 

It's all hands on deck at the site as walls start to go up and the cabling, brickwork & interior framing continue.

 

Works continue on the cabling and interior framing.

Today staff were able to test out the logistics of their new working space with a mock-up, to scale foam version of the new main bar!
 

Cabling is starting to appear all over the site and that's just the beginning! Interior walls are also starting to pop up.

 

The site is certainly starting to take shape and look more like a Club as the weeks go by.
Our builders are continuing their work on the interior brickwork and running to schedule which is great news!

 

Work continues on the interior framing and roof.

 

Lots of progress down at the site this week with the roof moving forward to completion and the interior steel framing going up fast!

 

Work continues on our roof as insulation is laid.

 

Work has officially begun on our brand new roof!

 

Our builders have returned from their Christmas break this week, with our roof being the next milestone we are working towards. The site should look quite different by this time next week!

 

Our builders are now on their well deserved Christmas break, returning early January when they will be working on the roof.

 

Some of the exterior brickwork is now going up and the builders are continuing to prepare for the roofing.

 

The steel framing is continuing to rise up!

 

Work continues as our builders continue to erect the steel framing

 

At this stage of the rebuild, progress is being made fast as steel framing nears completion.

 
Some progress shots of where we were at 18 weeks ago, where we are now & where we will be at complete of the build. Our Club is now starting to take shape!
 

The steel framing is going up fast and it's now getting easier to visualise what our brand new Club will look like.

 

The concrete slab is now complete. Next step is the steel framework.

 

We have reached a milestone with the final layer of concrete setting to form our ultrafloor.

 

We are getting close to finishing the ultrafloor despite the rain!

 

We are getting close to finishing the ultrafloor despite the rain!

 

Our builders are continuing to prepare the site for the concrete slab.

 

Our builders have now completed the steel formwork with bright blue bondek. We are still running to schedule which is great news

 
10 weeks in and our site is looking very different to a week ago! The ultrafloor is progressing nicely and more concrete is being poured.
 

This week our builders are continuing to prepare the foundations of our ultrafloor/slab. It's a big job! Before we know it they will be pouring the slab.

 

Despite the heavy rain this week, our builders are continuing to work on the ultrafloor.

 

This week our builders have started to pour concrete into the dincel walls, setting the foundations for our ultrafloor in place.

Rohrig rebuilding the Katoomba RSL

 

The dincel walls are almost complete! Next steps will be pouring concrete into the dincel walls and reusing the dirt mounds sourrounding the site to put back into the foundations.

 

Our builders were hard at work on Saturday pouring the concrete footings! We're making good progress!

Over the next few weeks, the dincel walls, otherwise known as waffle pods are being slit over the metal framing and concrete poured in to set the structures. This will form the base of our future floor!

 

This week the builders are making the final adjustments to the land and putting the steel framing in place before the concrete can be poured.

 

Our builders have been very busy on-site, leveling the land and putting the finishing touches on the trenches.